REHABILITATION WORK ON COMMUNITY ROAD CU9 (LOT1)

    • Place : KOUPELA – TENKODOGO – BITTOU – CINKASE – BORDER OF TOGO AND THE MOGANDE BRACKET (LOT 1)
    • Starting date : février 2015
    • Completion date : planned for April 2018
    • Length :  Length: 48.2 Km
    • 06 works of art
    • 36 hydraulic structures

REHABILITATION WORK ON COMMUNITY ROAD CU9 (LOT3)

    • Place : KOUPELA – TENKODOGO – BITTOU – CINKANSÉ – BORDER OF TOGO AND THE MOGANDE BROTELLE (LOT 3)
    • Starting date : February /2015
    • Completion date : planned for March/2018
    • Length : length 75.8 km
    • 97 hydraulic structures